Name of Project

Construction of new Kandarah 380/110/13.8kV BSP in Jeddah city

Client Name:

SEC-WRB

Location

Jeddah City

Value

494,729,040 SR

Completion Date

25 Months

Value:

494,729,040 SR

Turnkey Or Sub-Contract

Turnkey

Consortium

NA

Scope of Work:

  • The project is 380kv Substation with 10 Bays having 1500MVA Transformation Capacity to Feed 23 Nos 110kv Feeder at different susbsation .
  • The substation is inclusive of one reactor of 80 MVAR .
  • The substation will be connected with Jamia and KMT 380kv Substations with 380kv underground Cables.

  • This Substation will supply the Power to the Central areas & down Town of Jeddah City and enhance the power Grid capability in those areas.
  •  


     

     

    Name of Project

    Sharourah Power Plant Extension

    Client Name:

    SEC-SOA

    Location

    Sharourah City

    Value

    358,733,371 SR

    Completion Date

    23 Months

    Value:

    358,733,371 SR

    Turnkey Or Sub-Contract

    Turnkey

    Consortium

    NA

    Scope of Work:

    Engineering, Design, procure, supply and deliver all equipments and materials to the WORK SITE, construct, install, test and commission the extension of Sharourah Power Plant by:

  • - Adding two [2] Gas Turbine Generator Units by 33.996MW, their associated auxiliaries and Balance of Plant [B.O.P.] as GTG Unit # 1 and GTG Unit # 2 for Project Portion 1. - Adding one [1] Gas Turbine Generator Unit of 16.998MW, its associated auxiliaries and Balance of Plant [B.O.P.] as GTG Unit # 3 for Project Portion 2.
  • The Balance of Plant includes, Fuel tanks, Fuel treatment, Water treatment, Compressed Air system, Fire fighting, HVAC, Cranes, Civil Works, Switchgear building unloading bays, Electrical works includes GSU transformers, 33 & 4.16 kV Switchgear, Cabling, complete I&C including DCS, CEMS and other instrumentation works.
  • Any Other Detail

    Technical Partnership - CMEC, China


     

     

    Contract No. & Signing Date 534/22/3
    Client Name SEC-CRB
    Project/ Contract Title and Brief Description of Work

    CONSTRUCTION OF NEW 380KV S/S 9013 AT SHIFA AREA, SOUTH OF RIYADH

    DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF A NEW 380/132KV S/S# 9013 IN SOUTH OF RIYADH CITY TWELVE (12) BAYS, 380KV GIS, SEVENTEEN (17) BAYS 132KV GIS, THREE (3), 380/132/33KV 500MVA, POWER TRANSFORMERS AND ASSOCIATED CONTROL, PROTECTION, RELAYING METERING, AUXILIARIES, SCADA, TELECOMMUNICATION, FIBER OPTIC EQUIPMENT, (INCLUDING REMOTE END MODIFICATION S/S OF 380KV & 132KV INVOLVED), CABLES AND TWO DOUBLE CIRCUITS 380KV OHL (APPROX. 625 METERS EACH) AND CIVIL & ELECTROMECHANICAL WORK INCLUDING 380KV GIS BUILDING, 132KG GIS BUILDING, 380/132KV TRANSFORMER ROOMS AND CONTROL BUILDING ETC.,

    Contract Start Date 26-Oct-2003
    Contract Completion Date 26-May-2006
    Value (Saudi Riyals) 204,842,787

     

     

    Contract No. & Signing Date 2/1/23
    Client Name SEC-WRB
    Project/ Contract Title and Brief Description of Work

    CONSTRUCTION OF JEDDAH NORTH 380/110KV SUBSTATION (SWITCHGEAR, POWER TRANSFORMERS & CIVIL WORKS)

    DESIGN, SUPPLY, ERECTION & TESTING OF COMPLETE NEW SUBSTATION COMPRISING OF : 15 BAYS OF 380KV GAS INSULTED SWITCHGEAR, 25 BAYS OF 110KV GAS INSULATED SWITCHGEAR, 2 X 500MVA POWER TRANSOFRMER 7 1 X 60MVAR 380KV SHUNT REACTOR.

    Contract Start Date 10-May-2003
    Contract Completion Date 10-Aug-2005
    Value (Saudi Riyals) 172,206,392

     

     

    Contract No. & Signing Date 36/1/16
    Client Name SEC-WRB
    Project/ Contract Title and Brief Description of Work

    Construction of 380/110 kV Wadi Jaleel Outdoor S/S in Makkah (lot-1, Switchgear & Civil Works)

    380/110kV Outdoor Switchgear, Busbar System, Control and Protection, Auxiliary System, Civil and Mechanical Works, it is one of the largest construction jobs. Live Insulator Washing System installed for the first time in KSA.

    Contract Start Date 03-Apr-1997
    Contract Completion Date 01-04-2000
    Value (Saudi Riyals) 124,085,568

     

     

    Contract No. & Signing Date 23/10/-/-/Sheen
    Client Name EC
    Project/ Contract Title and Brief Description of Work

    CONSTRUCTION OF 40 MW POWER PLANT IN QURAYAT

    TURNKEY PROJECT FOR COMPLETE CONSTRUCTION OF POWER HOUSE & ASSOCIATE BUILDINGS, DISMANTLING, TRANSPORTATION AND REINSTALLATION OF 2 X 20 MW GAS TURBINES, 2 X 28.5 MVA POWER TRANSFORMERS, SUPPLY & INSTALLATION OF WATER, FIRE DETECTION / FIGHTING SYSTEMS, 2 X 1500 KVA, 13.8 / CABLES & TRANSFORMERS.

    Contract Start Date 1989
    Contract Completion Date 1992
    Value (Saudi Riyals) 61, 091,753

     

     