PE-63
| Contract No |
30441103/00 |
Project/Contract Title: |
Reinforcement Of 1st. Dammam Industrial city 69/13.8 Kv Ss # 2. |
Client Name: |
SEC-EOA |
Location |
Dammam |
Contract Start Date |
05-May-05 |
Completion Date |
05-Sep-08 |
Progress % |
95% |
Category: |
Mechanical, Civil, T&C, SCADA, E&I |
Project Type |
Turnkey |
Scope of Work: |
Extension of existing 69kV Outdoor Type Substation with one transformer bay which includes the following :-
69/13.8kV Power Transformer 30/40MVA
60kV Outdoor type Surge Arresters
69kV Circuit Breaker, Disconnect Switches
69kV CTs, VTs and wall bushing - 13.8kV Switchgear 2000A
13.8kV LV and Control Cables
Request for more details pertaining to this project – psmd@alfanar.com |
PE-66
| Contract No |
30431070/00 |
Project/Contract Title: |
Juaymah Area Reinforcement (Phase Ii) |
Client Name: |
SEC-EOA |
Location |
Juaymah |
Contract Start Date |
30-Jul-05 |
Completion Date |
29-May-09 |
Progress % |
87.31% |
Category: |
Mechanical, Cable, Civil, T&C, SCADA, E&I |
Project Type |
Turnkey |
Scope of Work: |
This is a turn key project and consists of Engineering & Design, Supply, installation, testing and commissioning of the following :-
115kV, 14 Nos bays - 115kV cables,
protection & control,
protection modification at 230kV Ghazlan & Juaymah NGL S/S,
Transmission Line
Request for more details pertaining to this project – psmd@alfanar.com |
PE-67
| Contract No |
27 |
Project/Contract Title: |
69/13.8kV S/Stn # 2 Distribution Feeders to KFU Substation tn# 4 |
Client Name: |
KFU |
Location |
……. |
Contract Start Date |
14-Oct-05 |
Completion Date |
……. |
Progress % |
96.23% |
Category: |
Mechanical, Civil, T&C, SCADA, E&I |
Project Type |
Turnkey |
Scope of Work: |
This is a turn key project and consists of Engineering & Design, Supply, installation, testing and commissioning of the following :-
69kV, 4 Nos. GIS bays
Two transformer 40MVA cable feeders complete with 13.8kV protection and control,
Civil and electromechanical work for the complete substation.
The new S/Stn will remotely controlled by SCADA system from the company power control
Request for more details pertaining to this project – psmd@alfanar.com |
PE-68
| Contract No |
20431074/00 |
Project/Contract Title: |
Construction Of The New Al-Sharaieh 110/13.8 Kv S/S |
Client Name: |
SEC-WOA |
Location |
Al-Sharaieh |
Contract Start Date |
18-Feb-06 |
Completion Date |
15-June-08 |
Progress % |
93.8% |
Category: |
Mechanical, Civil, T&C, Scada, E&I |
Project Type |
Turnkey |
Scope of Work: |
This is a turn key project and consists of Engineering & Design, Supply, installation, testing and commissioning of the following :-
40MVA Power Transformer
HV / MV / Control Cables
AVC Panels
SCADA & Telecom
Request for more details pertaining to this project – psmd@alfanar.com |
PE-69
| Contract No |
30131003/00 |
Project/Contract Title: |
Power supply to Haradh Crude Increment II |
Client Name: |
SEC-EOA |
Location |
Haradh |
Contract Start Date |
23-Feb-06 |
Completion Date |
19-Apr-08 |
Progress % |
98% |
Category: |
Mechanical, Civil, T&C, SCADA, E&I |
Project Type |
Turnkey |
Scope of Work: |
This is a turn key project and consists of Engineering & Design, Supply, installation, testing and commissioning for the left over portion of the work by terminated contractor M/s Gulf Potential and includes the following :-
AC / DC Distribution System
Protection System
SCADA
Grounding, Lighting, Transmission Line
Request for more details pertaining to this project – psmd@alfanar.com |
PE-69
| Contract No |
30531144/00 |
Project/Contract Title: |
Construction of 115/13.8 kV Al-Masoudi S/S |
Client Name: |
SEC-EOA |
Location |
Al-Masoudi |
Contract Start Date |
23-Feb-06 |
Completion Date |
30-Nov-08 |
Progress % |
66% |
Category: |
Mechanical, Cable, Civil, T&C, SCADA, E&I, Piping |
Project Type |
Turnkey |
Scope of Work: |
This is a turn key project and consists of Engineering & Design, Supply, installation, testing and commissioning of the following :-
115kV GIS Bays
115/13.8kV Power Transformers
13.8kV Switchgear Line Up
115kV Surge Arresters (Outdoor)
Control, Protection and Metering for complete substation
Medium density Fiber Optic Equipment
SCADA System
Civil work complete including buildings, trenches, etc
Mechanical, complete works
Indoor / Outdoor lighting works
Request for more details pertaining to this project – psmd@alfanar.com |
PE-74
| Contract No |
30631036/00 |
Project/Contract Title: |
Construction of New Saihat 115/13.8kV Substation |
Client Name: |
SEC-EOA |
Location |
Saihat |
Contract Start Date |
20-Nov-06 |
Completion Date |
11-Jan-09 |
Progress % |
52.13% |
Category: |
Mechanical, Civil, T&C, SCADA, E&I, Piping |
Project Type |
Turnkey |
| Scope of Work:
|
Contractor shall design, engineer, procure, supply and deliver all equipment and materials including operational spare parts and special equipment and or tools to the work site and company designated warehouse's) respectively, construct, install test and commission and put into service new Saihat 115/13.8kV S/S # 2 and the associated modifications to Al Dhahiyan 380/115kV bulk supply point (BSP) S/S as described below in accordance with the Scope of work and technical specifications, PTS-05EN122:
Request for more details pertaining to this project – psmd@alfanar.com
|
PE-75
| Contract No |
30631037/00 |
Project/Contract Title: |
Construction of HIE 115/13.8kV SS#2 & Modification of 13.8 kV Switchgear @RWPS SS |
Client Name: |
SEC-EOA |
Location |
……. |
Contract Start Date |
20-Nov-06 |
Completion Date |
11-Feb-09 |
Progress % |
63.36% |
Category: |
Mechanical, OHTL, Civil, T&C, SCADA, E&I, Piping |
Project Type |
Turnkey |
| Scope of Work: |
Contractor shall design, engineer, procure, supply and deliver all equipment and materials including operational spare parts and special equipment and or tools to the work site and company designated warehouses respectively, construct, install test and commission and put into service Hassa Industrial Estate (hereafter referred to as H.I.E) 115/13.8kV S/S-2 and the associated modifications to existing H.I.E 115/13.8kV S/S and Al Uyun 115/13.8kV S/S and new 13.8kV Switchgear and the associated modifications to existing RWPS 3C line valve #6 115/13.8kV S/S as described below in accordance with the Scope of work and Technical Specification, PTS-05EN128 and PTS-05EM129. The work consists of the following project portions.
Request for more details pertaining to this project – psmd@alfanar.com |
PE-76
| Contract No |
30631038/00 |
Project/Contract Title: |
Construction of New Al Qadisiyyah 115/13.8kV SS |
Client Name: |
SEC-EOA |
Location |
Al Qadisiyyah |
Contract Start Date |
20-Nov-06 |
Completion Date |
11-Dec-08 |
Progress % |
36.5% |
Category: |
Mechanical, OHTL, Civil, T&C, SCADA, E&I, Piping |
Project Type |
Turnkey |
| Scope of Work: |
Contractor shall design, engineer, procure, supply and deliver all equipment and materials including operational spare parts and special equipment and or tools to the work site and company designated warehouse's) respectively, construct, install test and commission and put into service new Al Qadisiyyah 115/13.8kV SS and the modification to existing North Mubaraaz 115/13.8kV S/S and Hasa Home Ownership 115/13.8kV S/S as described below in accordance with the scope of work and Technical Specifications, PTS-05EN120:
Request for more details pertaining to this project – psmd@alfanar.com |
PE-77
| Contract No |
30633046/00 |
Project/Contract Title: |
Power Supply to Saudi Aramco East West- Pump Station 3 (SS & OHL) |
Client Name: |
SEC-EOA |
Location |
…… |
Contract Start Date |
20-Nov-06 |
Completion Date |
11-Oct-08 |
Progress % |
74.67% |
Category: |
Mechanical, OHTL, Civil, T&C, SCADA, E&I, Piping |
Project Type |
Turnkey |
| Scope of Work: |
Contractor shall design, engineer, procure supply and deliver all equipment and materials including operational spare parts and special equipment and / or tools to the work site and company designated warehouse(s) respectively, construct, install, test and commission the following:
Project Portion – 1. Design, Supply, Installation & testing of 230kV Wasia substation expansion by 3 no 230 kV circuit breaker with Ct, S, 6 Nos 230 kV disconnector, port insulation AC/DC auxiliary protector & control and communication system along with expansion of SCADA, SDE & Fault recorder
The scope includes protection system enunciator & SOE expansion at Saudi Aramco E/W pumping station #3 for the related lines with Wasia Project Portion – 2. Design, Procurement & construction of 230kV(16.65 kilometers) double
Circuit lattice Steel overhead transmission line with 2 OPGW from Wasia 230kV substation to East west pump station # 3 S/S
Civil works. 230kV Substation portion.
Site development of existing Substation by now asphalting & fence
Building extension Works (steel building)
Gantry & outdoor equipment foundation
230kV OHTL
230kV double circuit TL Lattice Towers. About 54 nos of towers to be installed.
Route is going through desert area and major highway crossing is required.
Request for more details pertaining to this project – psmd@alfanar.com
|
PE-78
| Contract No |
30631041/00 |
Project/Contract Title: |
Construction o f 115kV OHTL for Jubail- Secondary industries SS Including Protection & Communication Works |
Client Name: |
SEC-EOA |
Location |
Al Jubail |
Contract Start Date |
20-Nov-06 |
Completion Date |
10-Dec-09 |
Progress % |
50.54% |
Category: |
OHTL, Civil, T&C, |
Project Type |
Turnkey |
| Scope of Work: |
Contractor shall design, engineer, procure, supply and deliver all equipment and materials including operational spare parts and special equipment and or tools to the work site and company designated warehouse(s) respectively, construct, install test and commission the required modification/additions to the protection, communication and SCADA equipment at Jubail Secondary Industries South (44BC) 115/3405kV S/S & Berri 230/115kV S/S in JIC in accordance with Scope of work and Technical Specifications, PTS-05EN125 and also construction of new 115kV double circuit overhead transmission line (including the installation of OPGW & U/G NFOC from the existing berri P/P to the existing Jubail Secondary Industries South 44BC S/S in accordance with the Scope of work and Technical Specifications, PTS-05ER118.
Project Portion – 1. Design, Procurement & construction of 7.5 km double circuit over head transmission line from Beri P/P to 44-BC transmission area using steel monopoles, ACSR “ Drake conductor 1-24 core OPGW & Conventional OPGW.
Project Portion – 2. Design, Procurement, & testing of line protection at both end of substation with extension & modification of SCADA, SOE & Fiber optic communication system
Civil Works – Jubail 11.5 kV OHL consists of 23 nos lattice steel towers, and 21 steel monopoles. The route length is 7.5 km and its is going in between other existing transmission lines in the same area
Request for more details pertaining to this project – psmd@alfanar.com
|
PE-78
| Contract No |
30631040/00 |
Project/Contract Title: |
Construction o f 115kV OHTL for New Saihat SS |
Client Name: |
SEC-EOA |
Location |
Saihat |
Contract Start Date |
20-Nov-06 |
Completion Date |
10-05-09 |
Progress % |
57.54% |
Category: |
OHTL, Civil, T&C, SCADA |
Project Type |
Turnkey |
| Scope of Work: |
Contractor shall design, engineer, procure, supply and deliver all equipment and materials including operational spare parts to the work site and company designated warehouses respectively, construct, install test and commission and put into service 115kV overhead transmission line and communication systems described below in accordance with the Scope of work and Technical Specifications, PTS-05EO127
Request for more details pertaining to this project – psmd@alfanar.com
|
PE-79
| Contract No |
10631061/00 |
Project/Contract Title: |
Construction of 132/13.8 kV SS. No. 8139 At King Abdullah Area in Riyadh City |
Client Name: |
SEC-COA |
Location |
Riyadh |
Contract Start Date |
22-Nov-06 |
Completion Date |
25-Jul-09 |
Progress % |
48.47% |
Category: |
Mechanical, Cable, Civil, T&C, SCADA, E&I, Piping |
Project Type |
Turnkey |
| Scope of Work: |
This is a turn key project and consists of supply installation, testing & commissioning
Request for more details pertaining to this project – psmd@alfanar.com
|
Completed Projects:
PE-62
| Contract No |
30441079/00 |
Project/Contract Title: |
Construction Of New Skaka Industrial 33/13.8KV ss |
Client Name: |
SEC-EOA |
Location |
Skaka |
Contract Start Date |
1/10/05 |
Completion Date |
07/03/08 |
Category: |
Mechanical, Cable, Civil, T&C, SCADA, E&I |
Sector |
Mechanical, Cable, Civil, T&C, SCADA, E&I |
Project Type |
Turnkey |
Scope of Work: |
This is turnkey project and consist of engineering & design, supply, installation, testing & commissioning ofthe following :-
5bays 33kV Switchgear, 1250A
2 Nos 20/25MVA, 33/13.8kV Power Transformer
13bay 13.8kV Switchgear, 2000A
1 Lot 33/13.8kV Cables & terminations
2 bays Extension of 33kV Switchgear at Al Jouf source S/S
1 Lot SCADA & Telecom, SOE, Annunciators, 33 control panels, relay panels
1 Lot 380V AC distribution board, batteries, DC distribution boards,
1 Lot Ring Main Unit